Feura Bush Water Filtration Plant Fluoridation Project
Albany
Summary
The fluoridation facility is built, but the city can't reliably get the chemical — much of it produced in Israel amid the ongoing war — so fluoridation hasn't started.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 2 meetings in the last 60 days; most recently Oct 29, 2026.
Impact analysis
The facility is complete; costs now hinge on chemical procurement.
Residents would gain cavity-prevention benefits once fluoridation begins.
Mentions & discussions (4)
Finance, Assessment and Taxation Committee - Oct 29, 2026
The fluoridation facility is built, but the city can't reliably get the chemical — much of it produced in Israel amid the ongoing war — so fluoridation hasn't started.
Water Board (Regular) - Sep 25, 2026
The board reviewed multiple contract change orders and adjustments for ongoing construction work at the Feura Bush Water Filtration Plant.
Water Board (Regular) - Mar 27, 2026
The Board approved change orders for general and electrical work on the fluoridation project at the Feura Bush Water Filtration Plant.
Municipal Water Finance Authority - Jan 29, 2026
Water officials announced that the start of water fluoridation has moved to March 2026, accompanied by new dam and storm sewer improvements.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Albany
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.